Ringwood Road, Poole (Hunt Road to Mountbatten roundabout)
Major work on bus, walking, cycling and road improvements including resurfacing along Ringwood Road between Hunt Road (Parkstone) and Mountbatten roundabout (Alderney/West Howe) started in September 2024. It forms part of a sustainable travel route planned between Poole, Ferndown and Wimborne which includes the new improvements on Wimborne Road, Leigh Road and Ringwood Road in Ferndown and St Mary’s Road in Poole.

What's being delivered
- A new northbound bus lane between St Clements Road and Old Wareham Road roundabout
- A new southbound bus lane from Mannings Heath Mini Roundabouts to Old Wareham Road roundabout
- 4.5km of road resurfacing from Hunt Road to Mountbatten roundabout
- Improving 1.8km of pavements on the western side of Ringwood Road between Hunt Road junction and Mountbatten roundabout including upgrading sections into shared paths for walking, wheeling and cycling
- A new 2.7km two-way cycle track on the eastern side of Ringwood Road, between Hunt Road junction and Mountbatten roundabout. This includes sections of shared path for walking, wheeling and cycling
- New and improved toucan, zebra and parallel crossings to enable east-west connectivity for people walking, cycling and wheeling along Ringwood Road. Click here for further details
- Major improvements to Sea View Road junction to improve the traffic flow for buses and motorised vehicles. A new dedicated bi-directional cycle crossing and new pedestrian crossing will be installed across Sea View Road
- 23 side road junction upgrades including improvements to bus, walking and cycling provision
- Upgraded bus stop shelters at 19 locations; five bus stops relocated. Click here for further details
- Improvements to Old Wareham Road roundabout including wider footways and new crossings on all arms
- Removal of dedicated right-turn filter lanes into Balston Road and Albion Close. Vehicles will still be able to turn right
- Removal of dedicated right-turn filter lane into Rossmore Road. The northbound lane will be widened so that vehicles can still turn right and northbound traffic able to pass stationary right-turning traffic
- Several trees will be removed between Old Wareham Road roundabout and Sea View Road. New and additional trees and landscaping will be planted as part of the final layout
- To support the improvements, the speed limit between Alderney roundabout and Mountbatten roundabout has been reduced to 30 mph to improve safety.
Detailed plans:
- Hunt Road – Sea View Road
- Sea View Road - Mannings Heath Mini Roundabout
- Mannings Heath mini roundabouts – Mountbatten Roundabout
Detailed general arrangement drawings of the plans on Ringwood Road:
- Hunt Road - Sea View Road
- Sea View Road - Mannings Heath Mini Roundabouts
- Mannings Heath Mini Roundabouts - Mountbatten Roundabout
For any problems interpreting the plans please email transformingtravel@bcpcouncil.gov.uk.
Work phases
Phase one
The first phase of work on Ringwood Road took place from 2 September 2024 until spring 2025 at two locations on Ringwood Road: Mountbatten roundabout to Alderney roundabout and at Sea View junction.

Phase two north - Alderney roundabout to Alderney Avenue
This phase of work was largely completed between February 2025 and May 2025. It should be noted that the tree planting and landscaping at Bedford Road South/Dolbery Road South will take place during the next planting season.
Phase two south - Hunt Road to Balston Road
Carriageway surfacing work will start on the evening of Monday 17 November 2025 and will take approximately four weeks to complete. Work will be undertaken with evening and overnight working.
It is anticipated the surfacing and lining work will be carried out in four phases, with each phase expected to take approximately 4-6 evenings/nights to complete. In order to carry out the work safely there will be a rolling closure of Ringwood Road (including side road junctions) to all vehicles as each phase is delivered. More information about the phasing order can be found in the table below.
Anticipated working dates have been provided for the first two phases and our contractor, M Group Highways, will be writing to properties whose access will be affected by the final two phases ahead of these phases starting. There will also be variable messaging signs located at Constitution Hill roundabout, Dorchester Road, and Sea View junction, which will provide information on the closure areas.
If work is taking place outside your property and the road is closed you will not be able to park on the road or access your driveway by vehicle. Vehicles parked on the road will need to be removed by midday on days where work is being carried out that night or they may risk being towed. If you need your vehicle during the hours of work, please park outside the closure area for that evening/night.
Works will be taking place during the evening and overnight closure hours, Monday-Friday only, as detailed in the table below, and we apologise for the inconvenience and disturbance this will cause. Work needs to be carried out during unsociable hours in order to minimise the impact on access for residents and businesses during opening hours. The majority of works have been restricted to evening hours; overnight works have been authorised only where completely necessary. All roads will reopen outside of these hours (including the weekend).
Working phases - anticipated dates and working hours
| Anticipated location on Ringwood Road | Anticipated traffic management | Anticipated dates and working hours |
Dorchester Road
|
Road closure of Ringwood Road, Dorchester Road, and Foxholes Road junction |
19:00-midnight on the nights of 17 and 18 November 2025. Work will be undertaken throughout these hours. Line marking operations may extend beyond midnight. |
South of Balston Road to Dale RoadIncluding the junctions of:
|
Road closure of Ringwood Road and the noted side road junctions |
19:00-06:00 on the nights of 19-21 November 2025 19:00-midnight on the nights of 24 and 25 November 2025 Line marking operations may extend beyond midnight. Work will be undertaken throughout these hours. |
Dale Road to south of Parkstone HeightsIncluding the following junctions:
|
Road closure of Ringwood Road and the noted side road junctions Please check on-road signage to see which sections will be closed each night. |
19:00-midnight Work will be undertaken throughout these hours Line marking operations may extend beyond midnight. Letter for access-affected properties to follow. |
|
South of Parkstone Heights to Constitution Hill roundabout
Hunt Road - Constitution Hill roundabout will be line marking only. |
Road closure of Ringwood Road and the noted side road junctions Please check on-road signage to see which sections will be closed each night. |
19:00-midnight Work will be undertaken throughout these hours Line marking operations may extend beyond midnight. Letter for access-affected properties to follow. |
Signed diversion routes will be in place, Pedestrian, cyclist and emergency service access will be maintained.
The following sustainable travel improvements are being delivered between Hunt Road and Balston Road:
- Two-way cycle path on the eastern side of Ringwood Road between Balston Road and Hunt Road, linking into previously constructed cycle paths to the north
- A new parallel crossing across Ringwood Road, just south of Haymoor Road, with associated areas of shared use path upon approach
- A new toucan crossing across Ringwood Road, just north of Dale Road, with associated areas of shared use path upon approach
- The pedestrian refuge on Ringwood Road just south of Dorchester Road junction is being upgraded to a toucan crossing
- Junction tightening at Haymoor Road
- Junction tightening at Dale Road with pedestrian refuge being removed
- Junction tightening at Kinson Pottery
- Two-way cycle path on the eastern side of Ringwood Road between Balston Road and Parkstone Heights, linking into previously constructed cycle paths to the north and south.
- Haymoor Road (southbound) bus stop to be relocated further south and shelter upgraded
- Dale Road (northbound) bus stop outside no. 192 Ringwood Road to be relocated to outside Nos 196 and 198 Ringwood Road, and shelter upgraded
- Dale Road (southbound) bus stop to be repositioned and shelter upgraded
- Footway surfacing
- Carriageway surfacing
- Improvement to street lighting.
Phase three - Old Wareham roundabout to Sea View junction
Work started on 14 April 2025 and is anticipated to last until early spring 2026. Work is being carried out using temporary road narrowing - traffic flow will still be two-way.
The following sustainable travel improvements are being constructed between Old Wareham roundabout and Sea View Road junction:
- A new northbound bus lane between St Clements Road and Old Wareham Road roundabout
- Footway on the western side to be upgraded to shared use path from Old Wareham Road to St Clement’s Road
- New two-way cycle track on the eastern side of Ringwood Road from Old Wareham Road roundabout to Sea View junction linking with those sections already complete to the south.
- Crossing improvements
- Crossing outside no 223/225 Ringwood Road to be upgraded
- Crossing adjacent to Cynthia House to be relocated slightly further north, closer to Tesco Express
- Zebra adjacent Rosemary Road – to be removed
- Upgraded bus stop shelters
- 4 bus shelters upgraded, remaining in same location
- Tesco bus stop (southbound) relocated to adjacent to Cynthia House
- All bus laybys are being removed
- Side road junction enhancements
- Removal of the dedicated right-turn filter lane into Albion Close. Vehicles will still be able to turn right
- Carriageway and footway resurfacing
- New landscaping and tree plantings.
Phase four - Old Wareham Road roundabout to Mannings Heath mini roundabouts
Work on this section commenced on 20 October 2025 and is anticipated to complete by summer 2026. The majority of work will be carried out under minor carriageway incursion only, however there will be some off-peak/night working under temporary traffic lights required.
Work is being carried out in phases. Our contractor, M Group Highways, will keep businesses and residents up to date as works progress.
Final surfacing works for this section will not take place until the very end of the works, and we will write to affected residents and businesses with more information about the surfacing works and associated traffic management at that time.
The following sustainable travel improvements will be constructed between Old Wareham Road roundabout and Mannings Heath mini roundabouts:
- New southbound bus lane from Mannings Heath mini roundabouts to Old Wareham Road roundabout
- Two-way cycle track on the eastern side from Mannings Heath mini roundabouts to just north of Old Wareham Road roundabout – connecting into the cycle track already delivered to the north and south
- New shared use path around Old Wareham Road roundabout, and up to No 558 on the western side
- New toucan crossing on Old Wareham Road outside Nos 12/14 and 526 Ringwood Road
- New toucan crossing outside No 524 and 329a/335 Ringwood Road
- Realignment of the uncontrolled crossing on the northern arm of Old Wareham Road roundabout
- New toucan crossing outside No 558 Ringwood Road (upgraded from a pedestrian refuge)
- Crossing on Herbert Avenue (near Manor Avenue) to be relocated towards Mannings Heath mini roundabouts, opposite the car dealership
- Existing staggered crossing point north of Mannings Heath mini roundabouts to be widened and upgraded to a toucan crossing
- Upgrading the bus stop to a bus shelter at No 548 Ringwood Road
- Removal of dedicated right turn into Rossmore Road – northbound carriageway will be widened to accommodate turning traffic, allowing northbound traffic to pass vehicles waiting to turn right
- Side road junction improvements
- Carriageway and footway resurfacing
- New landscaping and tree planting
- Banned right turn into St George Ave is to be maintained
It is currently anticipated that the works to Old Wareham Road roundabout will be carried out towards the latter stages of this phase.
Traffic Regulation Orders (TROs)
Full details of the traffic regulation order process and outcomes for these improvements are available here.
The improvements require changes to parking, with double yellow lines being introduced outside the following property numbers:
- 142 – 160 Ringwood Road
- 182- 200 Ringwood Road
- 206 – 232 Ringwood Road
- 244 - 252 Ringwood Road
- 47 – 59 Ringwood Road, and up to the bus stop on the eastern side
This will result in the removal of approximately 30 parking spaces (using BCP Council’s standard measure for parking lengths).
The introduction of these parking restrictions was subject to the outcome of a separate legal process. We invited comments on the proposed Traffic Regulation Orders (TROs) earlier in June 2022 and the TRO was recommended for approval in October 2022. Full details of the traffic regulation order process and outcomes.
Surveys were undertaken reviewing the parking levels in the area, over one week in April 2021 and 2022, at the same morning, lunchtime, and evening periods. The average occupancy across all roads surveyed was 47% in April 2021, and 45% in April 2022. These results suggest that there is available parking in adjacent and nearby roads to accommodate the loss of the parking spaces. View the results.
Public consultation
Public consultation on these proposals was undertaken May – June 2021. For the consultation, the proposals were split into three sub-sections: (Fernside Road – Sea View Road; Sea View Road – Mannings Heath mini roundabouts; Mannings Heath mini roundabouts – Mountbatten roundabout).
All responses were analysed and helped shape the final scheme designs. Reports summarising the results of the consultation are available here:
- Fernside Road – Sea View Road
- Sea View Road – Mannings Heath mini roundabouts
- Mannings Heath mini roundabouts – Mountbatten roundabout
A report detailing our responses to issues raised is available here.
A public information event about the proposals was held on 8 June 2022.
